DAYTONA Rising September Project Update

During the last month, Daytona International Speedway continued to move forward with the $400 million DAYTONA Rising redevelopment project. Key areas of the new motorsports stadium are beginning to take shape. Below is a breakdown of key accomplishments since the last update as well as upcoming construction activities.

Vertical Transportation:
• Installed escalators and elevators at West and East ends of the project
• Ongoing masonry near the West end of the project as well as in the center
• Continued concrete pours on metal decks
• Ongoing steel deck and detailing throughout the project
• Began installation of curbs in West end and just east of the start/finish line
Injectors:
• Began pouring concrete stairs for the far west Injector
• Finalizing structural steel installation

Neighborhoods:
• Finalizing initial development of neighborhood bars, guest services, bathrooms and bistro concessions
• Ongoing installation of HVAC systems in the West and East ends as well as just east of the start/finish line
Miscellaneous:
• Ongoing demolition of the Turn 1 grandstands

Race fans can follow the progress of the DAYTONA Rising project by visiting www.DAYTONARising.com

Social Media Auto Publish Powered By : XYZScripts.com